KIMBLE BRIDGE REPLACEMENT

Project Description
As part of the 2019/2020 approved Capital Budget, the County will replace Kimble Bridge, constructed in 1940 and located on Fingal Line (County Road 16) between Mill Road and Oneida Road in the Township of Southwold. An Ontario Structure Inspection Manual inspection completed in 2016 recommended replacement of the bridge due to severe concrete delamination and corrosion of the railing and abutment bridge components.
Construction Schedule
Tentative Start – July 15, 2020* Estimated Completion – September 30, 2020*
*Please note that the timelines are approximate and will vary depending on weather and other factors.
Construction Detour
The following Traffic Detour will be established.

Notices & Project Owner Correspondence
For the latest project updates click below:
Project Contacts
Brad Walt, CET E-mail: brad.walt@gmblueplan.ca Phone: (519) 672-9403 ext. 5224
Brian Lima, P.Eng. E-mail: blima@elgin.ca Phone: (519) 631-1460 ext. 117